Current progress figures for the construction site financed by the World Bank EASTRIP project:

Classroom block: 79.12% complete
– Student dormitory: 92.17% complete
– Fruit and vegetable processing block: 84.50% complete
– Dairy product processing block: 82.61% complete
– Powerhouse: 65.62% complete
– Infrastructure works: 22.65% complete

Overall site implementation stands at 76.80%. In addition to these construction activities, the greenhouse is currently operational and the student demonstration site is functioning and being used for practical training. Signed Memorandum of understanding with some partner institution to accelerate the teaching processing