Semi-Annual Progress Report (July8/2023-January 8/2024)

January, 2024 Holeta, Oromia, Ethiopia

Holeta Polytechnic College

Centre of Excellence in Agro-Processing (CEAP)

East Africa Skills for Transformation and Regional Integration Project (EASTRIP)

Contents

List of table…………………………………………………………………………………………………………………………….. 2

Abbreviations………………………………………………………………………………………………………………………….. 3

1.      4

1.1. Project Background……………………………………………………………………………………………………………… 5

1.2. Regional Flagship TVET Institute Background……………………………………………………………………………. 6

2.      6

2.1.PDO Indicators: Increasing Access to TVET programs;…………………………………………………………………. 7

2.2.PDO Indicators: Improving quality and relevance of TVET programs;………………………………………………. 8

3.ACTIVITY & INTERMEDIATE RESULT MONITORING…………………………………………………………… 9

3.1. Component 1: Strengthening selected TVET Institutions for high quality skills development in priority sectors; 9

DLR 1.1. Establishment of Project Implementation Unit…………………………………………………………………. 9

DLR 1.2. Establishment of Industry Advisory Board…………………………………………………………………….. 10

DLR 2.1. Number of student enrolments…………………………………………………………………………………… 12

DLR 3.1. Number of demand-driven programs……………………………………………………………………………. 13

DLR 3.2. Number of staff with industrial attachment…………………………………………………………………….. 14

DLR 3.3. Number of staff with exchange programs………………………………………………………………………. 16

DLR 3.4. Signing of MoUs……………………………………………………………………………………………………… 17

DLR 3.5. Number of Tracer study……………………………………………………………………………………………. 18

4.CONSTRUCTION OF CoE AND PROCUREMENT OF EQUIPMENTS………………………………………. 20

4.2 Equipment/ Machinery………………………………………………………………………………………………………… 24

5.PROCRUMENT UPDATE……………………………………………………………………………………………………. 25

6.SAFEGUARD FOLLOW UP…………………………………………………………………………………………………. 26

7.BUDGET FOLLOW UP :……………………………………………………………………………………………………… 28

8.Challenges…………………………………………………………………………………………………………………………… 30

9.ANNEXES…………………………………………………………………………………………………………………………. 31

List of table

Table.1. Increasing Access to TVET programs. ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,6

Table.2. Improving quality ad relevance of TVET programs. ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,7

Table 3. Establishment of Project Implementation Unit. ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, ,,,,,,,8

Table 4. Establishment of Industry Advisory Board,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,9

Table 5. Number of student enrolments,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,11

Table.6. Number of demand-driven programs,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,12

Table.7. Number of staff with industrial attachment,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,13

Table.8. Number of staff with exchange programs,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,15

Table.9. Signing of MoUs,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,17

Table.10. Number of Tracer study. ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,18

Table 11: Achievements of Intermediate Results of Component 1,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,19

Table 12. Construction Progress Summery,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,20

Table 13: Budget Utilization,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,26

Table 14. Annual Working Plan Matrix,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,30

Table.15. Complaints Report,,,,, ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,31

Abbreviations

ATVET           Agricultural Technical and Vocational Education Training

CEAP              Centre of Excellence in Agro-Processing

DLI                 Disbursed Linked Indicators

DLR                Disbursed Linked Result.

EASTRIP        East Africa Skills for Transformation and Regional Integration Project

ESIA              Environment and Social Impact Assessment

IUCEA            Inter-University Council for East Africa.

LS                    Lump Sum

MoLS               Ministry of labour and Skills

MoU                Memorandum of Understanding

M&E               Monitoring and Evaluation

NPCU              National Project Coordination Unit

PDO               Project Development Objective

RFU                Regional Facilitation Unit

SIP                  Strategic Investment Plan

TOR               Term of Reference

TVET              Technical Vocational and Educational Training

WB                  World Bank

1.      INTRODUCTION

1.1. Project Background

EASTRIP is a project designed to support the development of highly specialised Technical and Vocational Education and Training (TVET) programs as well as industry-recognised short term certificate level training, and will target regional priority sectors in transport, energy, manufacturing and ICT. The project development objective of EASTRIP is to increase the access and improve the quality of TVET programs in selected regional flagship TVET institutes and to support regional integration in East Africa. The project was approved on October 30, 2018 and is expected to close on December 31, 2024.

The Project was approved as an IDA credit and grant to the amount of USD 293 million-equivalent to the three participating countries of Ethiopia, Kenya and Tanzania for the implementation of the East Africa Skill For Transformation and Regional Integration and for coordination of the project activities by Inter-University Council of East Africa(IUCEA).The credit and grant is constituted by the compositions to be utilized over the 5 year term of the project, Ethiopia 150 USD, Kenya 60 USD and Tanzania 75 USD.

The borrower for this Ethiopia Project Component is the Ministry of Finance and Economic Cooperation for Ethiopia. The principal implementing entity for the project component is the Ministry of Labour and Skill for Ethiopia through the National Project Coordination Unit.

The objective of the sector policy level interventions shall be to create a national TVET enabling environment and provide overall coordination of the country component. The TVET institute level interventions shall be to strengthen and develop seven flagship TVET Institutes in the country.

Three East African countries will participate in the project, including Ethiopia, Kenya, and Tanzania these regional flagship TVET institutes were selected through a transparent and competitive two-stage process: (a) a long list of TVET institutes nominated by the Government based on national and regional priorities and (b) a final list of TVET institutes selected based on the recommendation by an independent technical committee. Based on these principles of government nomination and competitive selection, 16 Regional Flagship TVET Institutes were selected from the three participating countries. And Holeta Polytechnic College were one of the selected Regional Flagship TVET Institutes

1.2. Regional Flagship TVET Institute Background

Holeta Polytechnic College is one of the oldest government-owned colleges, established in 1975 in Oromia Regional State. Its location is particularly well-suited at a distance of 30km from the capital city (Addis Ababa) on the way to Ambo.

The College is currently providing training in the agricultural sector (Crop Production, Animal Production, Animal Health and Natural Resources) from level I to IV; in the industrial development sector (GMFA) from Level I to II; and in the Economic Infrastructure sector (ICT) from level I to IV based on the market need and assessment results. Recently, the College launched two Bachelor of Science degree programs; Dairy, Meet, Fruits and Vegetables processing technology to train Technical Vocational Education Training (TVET) trainers in collaboration with the Federal TVET Institute. The aim is to develop skilled technical education teachers that will train technicians for industries and companies working on Agro-processing in the country. These programs are some of the new programs of its kind and will need special attention in order to be successful. Currently, the college has 75 academics and 74 administrative staff with the capacity to enrol over 1,000 trainees per year.

The overall objective of the proposed Centre of Excellence in Agro-processing at Holeta Polytechnic College is to deliver quality outcome-based training to supply competent, motivated and innovative middle and low-level workforce with the necessary technological skills to ensure the implementation of an agriculture-led industrial economy of Ethiopia.

In order to ensure Holeta’s success as a Centre of Excellence in Agro-Processing (CEAP), the college will also strengthen its governance and management, institutionalise industry linkages, develop and review market-relevant and competency-based training programs, train the managers and teachers of the college, upgrade key training facilities and equipment, and provide support to non-project national TVET colleges. Furthermore, the college will establish teaching-factory workshops, and provide teachers in-service, farmers, and youth training. For the Implementation of the above mentioned activities the College has got US$ 21,850,000.00 from the World Bank Group.

2.     HIGH LEVEL RESULTS PROGRESS ASSESSMENT

2.1.PDO Indicators: Increasing Access to TVET programs;

To achieve the project outcomes, the project is investing in the expansion of access to TVET programs, with a specific target of at least doubling annual student enrolment, by implementing Strategic Investment Plan (SIP)and necessary technical assistance and guidance at RFTI.

Table.1. Increasing Access to TVET programs

Verifiable IndicatorsDLIBaselinePerformance (2023/24) QI&IICumulative
2019/20 – 2023/24
Traffic Light
TargetActual%TargetActual%
Student enrollment at regional flagship TVET Institutions (No.) 2.1  50  140  252>100  1010  2719>100
Student enrollment at regional flagship TVET Institutions (short-term program) (No.)2.1  –  100  101>100  760  1511>100
Student enrolment at regional flagship TVET Institutions (long term program) No.2.1  50  50  151>100  250  1208>100
Female student enrolment at regional flagship TVET Institutions (short-term program) No.2.1  –  20  18>100  120  647>100
Female student enrolment at regional flagship TVET Institutions (long-term program) – No.2.1  8  6  48>100  56  380>100
Regional student enrolment at regional flagship TVET Institutions (Short-term program2.1  –  10  11>100  10  11>100
Regional student enrolment at regional flagship TVET Institutions (long-term program) No.2.1  –  8  –  8  –

Traffic Light Legend: Achieved    Below targetOrange Light.png On progress    Not Yet progressed; Non_Applicable_3.png Not Applicable

As mentioned in the above table except the regional student enrolment in long term we have achieved all the target and this year we have enrolled 11 the regional student in short term program through collaboration with Federal Democratic Republic of Ethiopia Refugees and Returnees Services and the enrolled student those have Yemen and Eretria nationality.  

2.2.PDO Indicators: Improving quality and relevance of TVET programs;

Table.2. Improving quality and relevance of TVET programs

Verifiable IndicatorsDLIBaselinePerformance (2023/24)Cumulative
2019/20 – 2023/24
Traffic Light
TargetActual%TargetActual% 
Graduate employment rate six months after graduation (Percentage) 2.1  –  98%  67.29%  74.77  98%  67.29%  74.77Orange Light.png
Graduate employment rate six months after graduation (female students) (Percentage) 2.1  –  99%  77%  81.05  99%  77%  81.05Orange Light.png
Number of demand-driven programs developed and accredited by national TVET accreditation agencies or certified by industries (No.)3.1  2  19  47  >100  19  47  >100
Number of demand-driven short-term programs developed (No.)3.1  –  12  18  >100  12  18  >100
Number of demand-driven long-term programs developed (No.)3.1  2  7  29  >100  7  29  >100

Traffic Light Legend: Achieved    Below target Orange Light.png On progress   Not Yet progressed; Non_Applicable_3.png Not Applicable

According to the tracer study conducted in 2023, the employment rate of 2022/23 graduates of Holeta polytechnic College is 74.77%. When disaggregated by gender, the study result shows that female employment rate is 81.05% whereas male employment rate is 70.1%. The tracer study report is published on the college website (www.hpc.edu.et).      Developing and getting accreditation for demand driven programs is one of the core activities of the centre & the target plan under this DLR is already achieved

3.ACTIVITY & INTERMEDIATE RESULT MONITORING

3.1. Component 1: Strengthening selected TVET Institutions for high quality skills development in priority sectors;

DLR 1.1. Establishment of Project Implementation Unit

Table 3. Establishment of Project Implementation Unit

Sub-ComponentAnnual ActivitiesUnit of MeasurementQuarter IICumulative (QI&QII)TL
TargetActual%TargetActual%
          
Sc1Active Project Staff# Staffs8810088100
Sc1Recruitment of additional staff# Staffs22
Sc1Conducting governing board  Quarterly meetings# of meetings12150Orange Light.png
Sc1Financial Audit & exit conferences workshop)# of Report1110011100
Sc1Procurement Audit# of Report11 
Sc1Community sensitization Workshop on the project status & cross cutting issues# of Workshop1110011100
Sc1Capacity Building training for PIU & College Mgt.# of Training25

Traffic Light Legend: Achieved    Below target Orange Light.png On progress   Not Yet progressed; Non_Applicable_3.png Not Applicable

All the project implementation units are actively functioning as a targeted plan and we have planned recruitment of additional staff but are unable to recruit due to overlapping of activities and delay in preparing terms of references(ToR) for that specific assessment.

Financial audit for 2015 E.C budget year was conducted by the external auditor (consulting firm) and Community Sensitization Workshop on the project status & cross cutting issues also conducted as per targeted plan in second quarter. Capacity building training for PIU & College management was not conducted as per targeted plan due to overlapping activities and busyness of the College management members. Procurement audit is not yet progressed because this activity is planned to be carried out through national project coordination unit(NPCU), so it’s on schedule. 

During governing board meeting

Photo during Community sensitization on Project Status.

DLR 1.2. Establishment of Industry Advisory Board

Table 4. Establishment of Industry Advisory Board

Sub-ComponentAnnual ActivitiesUnit of MeasurementQuarter IICumulative (QI&QII)TL
TargetActual%TargetActual%
 DLR 2.1. Number of student enrolments        
SC1.2.2Consultative meeting with the industry and institutions# of WS  1110011100
SC1.1.10Annual Project review and Planning workshop# of WS  11100
SC1.1.9Quarterly Project Review workshop‘’111002150Orange Light.png
SC1.2.3Bi-Annual Industry Advisory board meetings#of Meeting11100
SC1.1.8Training on Property Administration and Inventory (for Admin staff)#of Training11100
SC1.6.1Experiences sharing visit to College Staff# Visit1110022100

Traffic Light Legend: Achieved    Below target Orange Light.png On progress   Not Yet progressed; Non_Applicable_3.png Not Applicable

Consultative meetings with industries and partner institutions were conducted which was planned under the quarter 1 and 2. In connection with this, industry representatives and some of the partner institutions, totally 19 participants, participated in the meeting.  The industry managers confirmed during consultative meetings that problems associated with cooperative training were due to lack of binding rules between the college and industries.

Annual Project review and Planning workshop was conducted at the beginning of the first quarter with concerned stakeholders i.e. with College Management, College Community as per planned. On the other hand, bi annual industry advisory board meeting was successfully conducted. As indicated in the table above, both consultative meeting and bi annual industry advisory board meeting were conducted as per the plan under the quarter 1 and 2 respectively with 100% achievement. 

Training on Property Administration and inventory for administration staff as well as experiences sharing visits to College Staff also completed according to the plan in the last two quarters.

Photo during Annual Project planning Review

Photo during Consultative Meeting with Partner industry and Institution

Photo during Industry Advisory Board meeting at Addis Ababa Jupiter Hotel.

Photo during experiences sharing visit to College staff

DLR 2.1. Number of student enrolments

Table 5. Number of student enrolments

Sub-ComponentAnnual ActivitiesUnit of MeasurementQuarter IICumulative (QI&QII)TL
TargetActual%TargetActual%
 DLR 2.1. Number of student enrolments        
SC1.2.4Providing accommodation and house rent for Regional student on short-term training# RS10111001011100
SC1.5.1Selection of consultant for contract administration, supervision and design modification%Complete2%14%
SC1.5.2Construction of College facilities%2025
SC1.5.3Preparation of design for renovationsLP5050
SC1.5.4Renovation of Classrooms, Offices, Hall and ,toilet, othersLP5075Orange Light.png
SC1.3.1Strengthening day-care facilities including developing guideline for day-care (ECC) centerLP671007070-Orange Light.png
SC1.4.1 Training on Animal Pregnancy testing technology (ultra-sonography operation, skill training on Artificial insemination and synchronisation),Animal product and by product quality test# of Training11Orange Light.png
SC1.3.2Conduct Skill and technology competition among trainers and trainees as well as awarding best 3 innovators, support community through technology# of Events11Orange Light.png

Traffic Light Legend: Achieved    Below target Orange Light.png On progress   Not Yet progressed; Non_Applicable_3.png Not Applicable

 This year (2023) we have enrolled 11 regional students in a short term program through collaboration with Federal Democratic Republic of Ethiopia Refugees and Returnees Services and the enrolled students who have Yemen and Eretria nationality and completed our target in the short term program of regional students. 

Photo during training delivered for regional student from Refugees(Yemen&Eritera)

Selection of consultant for contract administration, supervision and design modification was delayed due to slow response from the World Bank side for no objection, delay in short list of the bidder from technical committee of our College and still on schedule and we are lagging in implementing this assignment so its achievement is below target. And the implementation of Construction of College facilities was below target because of poor performances of the contractor and the details of this activity are explained separately under the construction summary.

Preparation of design for renovations and Renovation of Classrooms, Offices, Hall and toilet, others also delayed due to overlapping activity with the main construction facility.

As indicated in the table above 70% of strengthening day-care facilities including developing guidelines for day-care (ECC) centres was completed and the remaining percentage will be completed very soon in the next quarter.

The ToR for training on animal pregnancy testing technology (ultrasonography operation, skill training on Artificial insemination and synchronisation), animal product and by product quality test and Conduct Skill and technology competition among trainers and trainees as well as awarding best 3 innovators, support community through technology already approved and will be implemented very soon.

DLR 3.1. Number of demand-driven programs

Table.6. Number of demand-driven programs

Sub-ComponentAnnual ActivitiesUnit of MeasurementQuarter IICumulative (QI&QII)TL
TargetActual%TargetActual%
 DLR 3.1. Number of demand-driven programs        
SC1.3.3Conduct Labour Market Need Assessment Study & Its Validation# of study11100
SC1.3.5Conduct marketing and promotion campaigns for Centre programs and services# of Campaigns1110011100
SC1.1.11Procurement of IT & Electronic equipment(Details in procurement plan ) %53.35093.8047.75o100
SC1.3.7Procurement of FurnitureLP110011100

Traffic Light Legend: Achieved    Below target Orange Light.png On progress   Not Yet progressed; Non_Applicable_3.png Not Applicable

Under this DLR all planned activities were successfully completed i.e. Conduct labour market need assessment and its validated college management as well as by concerned stakeholders and marketing and promotion campaigns for Centre programs and services achieved then it contributed a good success in student enrolment. Procurement of IT & Electronic equipment as well as furniture completed for the planned target and disturbed to concerned College staff.

DLR 3.2. Number of staff with industrial attachment

Table.7. Number of staff with industrial attachment

Sub-ComponentAnnual ActivitiesUnit of MeasurementQuarter IICumulative (QI&QII)TL
TargetActual%TargetActual%
 DLR 3.2. Number of staff with industrial attachment        
SC1.2.6Provide tailor made training to the industry trainers(training methodology for industry trainers)# Training11100
SC1.4.2Supply and Installation of TVET Institution Campus NetworkLP11
SC1.3.8Internship attachment for agro-processing students# attachment  34  42     >100  34  42>100
SC1.3.9Procurement of cables for agro-processing machineLP11
SC1.4.3Expand Dairy farms (procurement of heifers and improving barn)#of Heifers4
SC1.2.7Teachers Industrial Attachment Programs# Trainees  3  3  100  6  4  66Orange Light.png

Traffic Light Legend: Achieved    Below target Orange Light.png On progress   Not Yet progressed; Non_Applicable_3.png Not Applicable

Creating cordial relationships with industry partners is essential. Thus, the college provided Tailor made training to the 18 practitioners of industry and partner institutions. We Achieved 100% on tailor-made training designated under quarter two. Accordingly, the majority of the participants were happy and possessed necessary skills and knowledge from the training. Moreover, accordingly, the majority of the participants were happy and possessed necessary skills and knowledge from the training.  On the other hand, internship attachments for the Agro processing trainees were also conducted to 42 trainees with 123% achievements i.e above the target in the quarters. With regards to teacher’s industry attachments, four teachers were attached to the industry. To achieve the targets entitled under the quarters, two teachers were on the track to start industry attachment. Supply and Installation of TVET Institution Campus Network planned to be carried out through national project coordination unit but it’s not yet progressed and also the other activities which not yet progressed was procurement of cables for agro-processing machines due to delay in preparing specification for the cable.

Photo during Internship attachment for agro-processing students

DLR 3.3. Number of staff with exchange programs

Table 8. Number of staff with exchange programs

Sub-ComponentAnnual ActivitiesUnit of MeasurementQuarter IICumulative (QI&QII)TL
TargetActual%TargetActual%
 DLR 3.3. Number of staff with exchange programs        
SC1.4.4Sending teaching staff to undertake exchanges in another country# of teaching Staff55
SC1.1.12  Experience sharing  at sister college on gender issue & Construction # visit1110011100
Sc1.1.13Benchmarking Experience sharing for PIU and college Management abroad.# of Visit11

Traffic Light Legend: Achieved    Below target Orange Light.png On progress   Not Yet progressed; Non_Applicable_3.png Not Applicable

As indicated in the above table, the number of teaching staff who undertake exchanges in TVET institutes in another country is still not yet materialised due to reluctance of EASTRIP beneficiary countries to accommodate our trainers for staff exchange. On the other hands, overseas experience sharing visit to PIU and Management Staff is on the way and will be materialised in the next quarter

Photo During Gender & Construction related Experiences sharing at Jimma University

DLR 3.4. Signing of MoUs

Table.9. Signing of MoUs

Sub-ComponentAnnual ActivitiesUnit of MeasurementQuarter IICumulative (QI&QII)TL
TargetActual%TargetActual% 
 DLR 3.4. Signing of MoUs        
SC1.6.2Capacity building training for other college staff, teachers in-service, farmers, youth, and technicians (Detail in Training Plan)# of Training1110011100
SC1.4.5Capacity building on project base training for academic staff# of Training11100
SC1.4.6Training on laboratory technic analysis on agro-processing & animal health# of Training11
SC1.4.7Training for on Pedagogy for Higher Education(HDP)# of Trainees110011100
SC1.5.5Maintenances of Combiner & Tractor# Maintenances10.550%10.550%Orange Light.png
SC1.1.15Monthly & Bi-annual GRM committee meeting# of meeting36

Traffic Light Legend: Achieved    Below target Orange Light.png On progress   Not Yet progressed; Non_Applicable_3.png Not Applicable

Capacity building training for other college staff, teachers in service, farmer’s youth which is designed for four events, first round training was successfully provided to the 42 farmers and youth. The training was both theoretical and practical. Consequently, the farmers and youth were very happy with the training they have possessed; the remaining training for   other college staff and teacher in service is planned for the next quarters. Monthly & Bi-annual GRM committee meeting was not conducted due to no problem happened concerning GRM

Photo during project base training for academic staff

DLR 3.5. Number of Tracer study

Table.10. Number of Tracer study

Sub-ComponentAnnual ActivitiesUnit of MeasurementQuarter IICumulative (QI&QII)TL
TargetActual%TargetActual%
 DLR 3.5. Tracer study        
SC1.1.16Preparation of Business Plan for Income generation# Report5030601007070Orange Light.png
SC1.3.10Conduct ISO17025 Certification# Document  21.671569.12
SC1.2.8Providing Scholarship Agro-ProcessingLP11  
SC1.4.8strengthening  Agro-processing Department(CoE)LP11
SC1.6.4Promotion & Support Of  Alumina AssociationLP11

Traffic Light Legend: Achieved    Below target Orange Light.png On progress   Not Yet progressed; Non_Applicable_3.png Not Applicable

Even though it is difficult to quantify the progress of the  preparation of a business plan for income generation, about 70% of the assignment was completed as the expertise provided data. so it’s under progress. Providing scholarship agro-processing, strengthening agro-processing department(CoE)and promotion & support of alumina association was not yet progressed due to overlapping activities and delay in identifying the par meter for these activities.

Table 12: Achievements of Intermediate Results of Component 1

DLIsBaselineEnd Target2023/24CumulativePercentageTraffic Light 
TargetActualTargetActual  
DLR 1.1: Number of regional flagship TVET Institutions whose project implementation units are established (No.)088988100 
DLR 1.2: Number of flagship TVET Institutions whose industry advisory boards/committees are established with 50% representation of the private sector (No.) 099999100 
D.L.R 3.2.Teaching staff in RFTIs who have industrial attachment0       12     441212100 
DLR3.3.Teaching staff who undertake exchanges in another country083888100 
DLR3.4 MoUs signed with partner institutions (Number) 0183231823100 
Training condition improved and key training facilities provided (text)No100% completion31.98% completed13.9877.36% completed18.8024.30 
Income generation by flagship TVET Institutions (Amount(USD)) 0.2mil.USD0.1mil46168.160.2mil.USD0.1370.685Orange Light.png 
DLR 3.5: Tracer study conducted annually (Number) 0515360Orange Light.png 

Traffic Light Legend: Achieved     Below targetOrange Light.png On progress    Not Yet progressed; Non_Applicable_3.png Not Applicable

4.CONSTRUCTION OF CoE AND PROCUREMENT OF EQUIPMENTS

Table 12. Construction Progress Summary

 Graphical Progress of the construction

 
 

Plan           Executed

Holeta Polytechnic College Construction Projects 
Grand Summary of Bills 
 Bill ListContract Amount% (each bill Vs Total)To date Executed Amount% Execution progress vs ContractRemark
 1 Bill No.01 Class Room          188,225,902.40               0.27      21,895,995.3411.63w/o VAT 15%
 2 Bill No.02 SB+G+1 Teaching Factory(Dairy Product Processing)         117,320,088.75               0.17      19,496,848.8616.32 
 3 Bill No.03 SB+G+1 Teaching Factory (Fruit and Vegetables Processing  )         137,265,203.70               0.19      31,932,506.6023.62 
 4 Bill No.04 SB+G+4 Student Dormitory         168,322,449.75               0.24      62,898,305.7327.37 
 5 Bill No.05  Power House             6,981,322.75               0.01 – – 
 6 Bill No.06 Infrastructure Work           86,441,317.20               0.12           182,700.000.211 
  A) Sub Total         704,556,284.55               1.00    136,406,356.5319.36w/o VAT 15%
  Provisional Sum           21,000,000.00    
  Add 15% VAT = 15% of A         108,833,442.68       20,460,953.48  
  Grand Total without Provisional Sum         810,239,727.23     156,867,310.0119.36With 15% VAT but not Provisional Sum
  Grand Total with Provisional Sum         834,389,727.23     156,867,310.0118.80With 15% VAT  with Provisional Sum

a) Dairy & Fruit as well as Vegetable Teaching factory

b) Class Room                                                                   

c) Dormitory                                                                                                                                

4.2 Equipment/ Machinery

Procurement of Equipment and Machinery for the Dairy Product Processing Plant and Fruit and Vegetable Processing Plant through International Competitive Bidding (ICB)

Since the procurement process of this activity will be conducted through an ICB and at the same time prior review by the bank and the bidding document was changed to rated criteria. Thus, due to the change of request for bid (RFB) through ICB, even though the preparation of specifications for the dairy product processing plant and fruit and vegetable processing plant equipment and machinery has been completed, we are waiting from the bank for the new RFB. And the bank team has already informed us that they are facilitating training on the new rating criteria for requests for bids.

5.PROCUREMENT UPDATE

S NDescriptions of Procurement ActivitiesPro. Ref. No.Estimated Cost in USDProcurement CategoryMethod of ProcurementStatus as of December 31st 2023Next Action to be Taken
1Recruitment of Construction LawyerET-ET HOLETA-382026-CS-INDV25,000.00Consultant ServicesOpen – NationalWaiting for TOR to advertise Request for Expression of InterestThe TOR was will be prepared
2Recruitment of Quantity Surveyor Engineer for the Construction of College facility and Site work which is undergoing.ET-ET HOLETA-382025-CS-INDV25,000.00Consultant ServicesOpen – NationalWaiting for TOR to advertise Request for Expression of InterestIt is expected that the TOR will be approved by the Bank Team
3Training on Property Administration and Inventory (for Admin staff)05,000.00Non-Consultant ServiceLimited/ShoppingCompleted (The Training was delivered)
4Selection of Consultant for Works Contract Administration, Construction Supervision and Design Modification (If any)ET-ET HOLETA-382235-CS-QCBS331,000.00Consultant ServicesOpen – NationalThe Short listing Evaluation Report is finalized. Invitation of Request for Proposal to the shortlisted consultant firms
5Procurement of Furniture for office & Meeting HallET-ET HOLETA-382043-GO-RFQ65,000.00GoodsLimited/ShoppingCompleted
6Procurement of IT & Electronic Equipment’sET-ET HOLETA-382029-GO-RFQ.85,000.00GoodsLimited/ShoppingCompleted

6.SAFEGUARD FOLLOW UP

NoInspection itemsYesNoNARemark
1Has the contractor appointed an Environmental and Social expert supervisor on-site?    
2Is the site kept clean and tidy (e.g. litter free, good housekeeping)?    
3Are chemicals/hazardous products and waste stored on impermeable surfaces in secure, covered areas?  NA 
4Is there oil spillage at the site?    
5Are chemicals stored and labelled properly?  NA 
6 Is construction equipment well maintained (any black smoke observed)?    
7Is there an access road that was showering to minimum   dust emission?    
8Are there enclosures around the main dust generating activities?    
9Does the contractor regularly consult with nearby residents to identify concerns?    
10Is there any excessive noise?    
11Any noise mitigation measures adopted (e.g. use noise barrier / enclosure)?    
12Is construction wastewater and domestic wastewater discharged to sewer systems (if possible), or are on-site treatment facilities (septic tank) provided?    
13Is there any wastewater discharged to soil or surface water    
14Are separated labelled containers/areas provided for facilitating recycling and waste segregation?    
15Are construction wastes/recyclable wastes and general refuse removed off site regularly?    
16Is safe supply of clean water and an adequate number of toilets provided for workers by considering sex?    
17Is personal protection equipment provided for workers and used properly?   Partially complies
18Are clear information and warning signs placed at construction sites in view of the students and staff as well as the public?    
19Are all construction sites made secure, discouraging access through appropriate fencing?    
20Are disturbed areas properly re-vegetated after completion of works?    
21Were any complaints filed with the contractor, and have staff and nearby residents raised any concerns related to the performance of the contractor?   By the staffs
22Any other problems identified or observations made?    
23Lack of road signs or any required sign boards such as hazardous material storage area, explosive magazine, et  NA 
24Are there Safety helmets and rubber gloves and boots to the labourers to avoid worksite hazards and accidents?   Partially complies
25Protective footwear, goggles and clothing to all workers employed on lying of wearing coat, preparing cement mortars for brick work, concreting, painting etc   Partially complies
26Welder’s protective eye-shields to workers who are engaged in welding works    
27Earplugs to workers exposed to loud noise, and workers working with jack hammer, joint cutting machines and Gloves provided?    
28Is there a dry waste collection waste bin at site?    
29Is there a contractor that employs women and pays equal wage with men for the same position work?    
30Is there any Gender violence at the site?    
31Is there a contractor to arrange close changing areas for both sex separately?    
32Is there soil disposal properly disposed of?    
33Is there any damage happening to flora and fauna?    
34Are there any workers employed under the age of 15?    
35Are there any accidents and incidents at the site?   Collapse of machinery but no accident on worker. 
36Is there an accident and incident recording, get a book at the site?    

Gender

  • The key concern of college governance and leadership is to secure high-level commitments to gender equality. The Board of Directors, the dean, senior management and other top representatives of the College developed and aware strong leadership on the topic of gender equity and equality in core activities, management and support processes, organizational culture and policies of the College.
  • A look at the existing structure reveals regarding of government’s requirement establish a gender office or focal point in public and private organizations, there is gender office or focal point to enhance gender integration in the activities of the College.
  • Women are underrepresented in the college before. In 2023/2024 the number of women representation in management positions or decision making (7 college managers) is increase from 1 to 3 (3 women out of the 7 board members). where both women and men are decision makers
  • Holeta polytechnic college gender office is networked with, Holeta town women and child affair berou and support by providing training on different gender issue.
  • Creating an environment of involvement for both male and female and enhance female employees and students at their work and education day care centre was establish in the college.
  • Female and disable groups are well treated regarding provision of tutorial class, support of material, aware on gender based violence and conducive environment were creating to insure   Fair and sustainable development.

7.BUDGET FOLLOW UP:

Table 13: Budget Utilisation of HPC

DLRsAnnual BudgetSemi-AnnualBudget Utilisation Performance (%)
BudgetExpendedSemi-AnnualAnnual
DLR  1.1  Establishment of Project Implementation Unit complied36,072,931.7518,052,558.886,133,828.5433.9017
DLR  1.2  Establishment of Industry Advisory Board Meeting5,404,729.723,457,787.752,349,428.5667.9043.40
DLR 2.1.   Number of Student Enrolments530,412,487.87137,711,433.58167,880,745.01121.9031.60
DLR  3.1  Number of Demand Driven Programs120,758,378.004,262,060.40  1,601,790  37.501.3
DLR  3.2  Number of  staff with Industrial attachment32,984,304.0032,436,028.18297,947.410.900.90
DLR  3.3  Number of Staff with exchange programs5,901,314.404,262,060.40723,598.0016.9012.20
DLR  3.4  Signing of MoUs4,261,350.013,360,470.70666,617.8919.8015.60
DLR  3.5  Tracer Study4,259,164.382,021,746.60106,250.005.202.40
Total740054660.13205,564,145.49179,760,205.1487.4024.20

Financial Disbursements as per PAD and Recommendations by IVA up to year 5

DLIDLRTotal fund in USDPAD Max Allocation up to year 5Recommended up to year 5Absorption Rate up to year 5
DLI 1. Institutional readinessDLR 1.1. Establishment of Project Implementation Unit1,092,500   
DLR 1.2. Establishment of Industry Advisory Board1,092,500   
DLI 2. AccessDLR 2.1. Number of student enrolment3,277,5003,277,5003,017,65492.07
DLI 3. Quality DLR 3.1. Number of demand-driven programs3,277,5003,277,5003,277,500100
DLR 3.2. Number of staff with industrial attachment3,277,5003,277,5003,277,500100
DLR 3.3. Number of staff with exchange programs3,277,5003,277,5003,277,500100
DLR 3.4. Signing of MoUs3,277,5003,277,5003,277,500100
DLR 3.5. Tracer study3,277,5003,277,5002,042,62562.32
Total21,850,00019,665,00018,170,27992%

8.Challenges

  • Procurement of Equipment and Machinery for the Dairy Product Processing Plant and Fruit and Vegetable Processing Plant through International Competitive Bidding (ICB) unable to proceed due to the change of request for bid (RFB) of ICB
  • Slow response in recruitment of the Selection of consultant for contract administration, supervision and design modification from the bank side & sluggish from technical comment of our College in the short list of the bidders.
  • Slow progress in construction
  • Geotechnical variation from design
  • Shortage of cement specially OPC